To ensure clarity for project leads and clients, a detailed report should be structured with the following key elements:
| Trade | Planned Headcount | Actual Headcount | Notes | |-------|------------------|------------------|-------| | Mechanical fitters | 8 | 7 | One on sick leave (returns April 13) | | Electricians | 10 | 10 | – | | Plumbers | 6 | 6 | – | | Helpers / Laborers | 4 | 4 | – | | | 28 | 27 | – | mep work progress report sample
Here is a sample MEP work progress report: To ensure clarity for project leads and clients,
5 Material Inspection Requests (MIRs) submitted; 4 approved, 1 pending. Site Inspections: Weekly walkthrough completed with the MEP Consultant. building or an industrial warehouse mep work progress report sample